Case Details:
Case Number:
2025-00276
Case Status:
Open
Utility/Industry Type :
Electric
Utility/Industry Subtype :
Transmission and Distribution Utilities (T and Ds)
Case Type :
REQUEST FOR APPROVAL
Case Subtype :
CERTIFICATE OF FINDING OF PUBLIC CONVENIENCE & NECESSITY
Pertaining to Utility/Company :
CENTRAL MAINE POWER COMPANY
Case Title :
REQUEST FOR APPROVAL OF CERTIFICATE OF FINDING OF PUBLIC CONVENIENCE & NECESSITY FOR THE CONSTRUCTION OF THE GREATER PORTLAND TRANSMISSION UPGRADES PERTAINING TO CENTRAL MAINE POWER COMPANY
Initiating Filer :
CENTRAL MAINE POWER COMPANY
Case Start Date :
9/9/2025
Assigned Staff :
Dale.Coty,
Emily.Felt,
Kerri.A.Dill,
Paulina.Collins,
Rebecca.McMahon,
Romayn.Richards,
Sally.Zeh,
Michael.Simmons,
amy.mills,
kerri.dill,
Briana.Littlefield,
robert.a.creamer
View Case References
Filings (184)
Data Requests (10)
Public Comments (57)
Active Party and Notification List (121)
Assigned Staff (12)
Loading...
Item No.
Date Filed
Description Of Filing
Filing Party
Filed By
No of Attachments
Deleted Filings
184
10/26/2026
Letter from Falmouth Schools
TOWN OF FALMOUTH
Causey, Adam
1
183
10/23/2026
Comments of Intervenor Lily Morgan Regarding Proposed Route Changes, Property Impacts, and Communication with Affected Landowners
Morgan, Lily
Morgan, Lily
1
182
10/23/2026
Late Intervenor Filing
Goodman-Brown, Sandi
Goodman-Brown, Sandi
1
181
10/23/2026
Public Comments of James Macisso
Macisso, James
Macisso, James
1
180
10/23/2026
Office of the Public Advocate's Comments on Recommended Decision
OFFICE OF THE PUBLIC ADVOCATE
PUBLIC ADVOCATE, MAINE OFFICE OF THE
1
179
10/23/2026
Procedural Order (Response to Woodlands Motion and Late-Filed Interventions)
COMMISSION STAFF, CMS
COMMISSION STAFF, CMS
1
178
10/23/2026
Comment and Limited Exception of the Landowner Intervenors
Manzelli, Amy
Manzelli, Amy
1
177
10/23/2026
CMP Exceptions re Intervenor Funding
CENTRAL MAINE POWER COMPANY
CMP Regulatory Administration, Mariah Crommett
1
176
10/22/2026
Notice of Ex Parte Communications
COMMISSION STAFF, CMS
COMMISSION STAFF, CMS
1
175
10/22/2026
Public Comments of Stephen Champagne
Champagne, Steve
Champagne, Steve
1
Per Page
1
of
19
First
Prev
Next
Last
Go To
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
View By Set
View By Question
Loading...
DR Set ID
Set Description
Issue Date
No. of DR Questions
Propounded Upon
View Questions in Set
View Cover Letter/Instructions
Print
ACAUS-001
Dimensioned plans or renderings of proposed infrastructure and its relation to existing CMP infrastructure within the Town of Falmouth
8/6/2026
1
CENTRAL MAINE POWER COMPANY
View Questions
View
ALEN-001
Adequacy of the Review
8/13/2026
6
CENTRAL MAINE POWER COMPANY
View Questions
ALEN-002
Asset Condition
8/13/2026
14
CENTRAL MAINE POWER COMPANY
View Questions
ALEN-003
General
8/13/2026
1
CENTRAL MAINE POWER COMPANY
View Questions
ALEN-004
NWAC Review
8/13/2026
3
OFFICE OF THE PUBLIC ADVOCATE
View Questions
AP01-001
Data Requests of the Falmouth Corridor Intervenors to Central Maine Power Company regarding the Phase 1 Project. See attached cover letter for full party list, procedural basis, reservation of rights, and scope.
8/12/2026
21
CENTRAL MAINE POWER COMPANY
View Questions
View
DOER-001
Project Cost Recovery
8/13/2026
4
CENTRAL MAINE POWER COMPANY
View Questions
EXM-001
NWAC Report
8/12/2026
12
OFFICE OF THE PUBLIC ADVOCATE
View Questions
EXM-002
CPCN Costs
8/13/2026
30
CENTRAL MAINE POWER COMPANY
View Questions
EXM-003
CPCN Needs and Solutions
8/13/2026
49
CENTRAL MAINE POWER COMPANY
View Questions
Per Page
1
of
2
First
Prev
Next
Last
Go To
1
2
Loading...
Posted By
Posted Date
Comments
Attachment(s)
D. Kelekyan
Overset Rd, Portland
Email ID: dkelekyan@gmail.com
10/26/2026
Having just recently become aware of CMP's plans, I am deeply concerned about the impacts on my North Deering neighborhood. Like many of my neighbors, I have a few questions that should be addressed publicly: Why did CMP not communicate with us or let the neighborhood know in advance of their plans? What is the rationale for such an intrusive expansion in a suburban neighborhood with small lots in close proximity to each other? Have the impacts to the forestry, wetlands and wildlife been studied? What are the health and safety implications of the project for our community, especially the many houses that are very close to the current and planned lines, many of them with small children and pets. Have ALL potential alternatives been considered (such as underground lines through this small stretch, or relocating the lines along the railway/highway)? I feel very strongly that the project should be put on hold until the full impacts to our communities have been assessed and explained and less disruptive and intrusive alternatives given serious consideration.
Teresa S. Pierce
Maine State Senate
3 State House Station Augusta, ME 04333
Email ID: teresa.pierce@legislature.maine.gov
Phone No.: 2072871515
10/26/2026
Letter attached.
Pierce CMP Project Letter.pdf
Geoffrey S Emanuel
retired
4 Winding River Lane
Email ID: gesail@aol.com
Phone No.: 8178769412
10/26/2026
How much more would it cost to run lines on a route which would remain further away from less houses and the school. I would suport a electircity cost increase to fund that
Amy D. Kuhn
P.O. Box 66831 Falmouth, ME 04105
Email ID: Amy.Kuhn@legislature.maine.gov
10/26/2026
See letter attached.
Kuhn Public Comment.pdf
Erik Chuang
13 Alpine Drive, Falmouth ME 04105
Email ID: erikchuang@yahoo.com
Phone No.: 6462833067
10/25/2026
I live on Alpine Drive in Falmouth and the proposed power lines would impact my neighborhood and my child who attends the Falmouth school system. The proposed transmissions lines are entirely inappropriate to be run through these communities. The manner in which this proposal has been moving forward, effectively "under the cover of darkness", speaks to the lack of integrity in how the needs were determined, the alternatives considered, and the community engaged. I have concerns about impacts to health, property values and neighborhood character. There are several criticisms as to the need for this project (e.g., history of poor demand forecasting, weak consideration of alternatives), and CMP owes the public answers to those specific points without attempting to distract with corporate talking points that actually evade the questions.
Corvo
17 Pride Farm Rd, Falmouth, Maine
Email ID: hoppinorange@gmail.com
10/24/2026
My name is Brendan Nowak, and in my spare time I research restoration ecology, sustainable forest managent and do habitat restoration involving the removal of invasive plant species and planting of native plants. I am deeply opposed to the CMP corridor project, which I will not refer to as the NECEC since the name is clearly being used as a green washing tactic to gain public favor. While I support infrastructure upgrades that benefit the public and industry, this project is clearly being used to increase CMPs and HydroQuebecs profits, while putting the burden on rate payers and federal funding from our tax dollars to fund this project. CMP has made it very clear that they aren't interested in providing effective power transmission at a reasonable cost, but are purely focused on increasing their profits to give to their executives and funnel Mainers money into foreign stock holders, like the Qatari royal family, who owns the largest share of Iberdola stock. I am also deeply concerned with the greenwashing rhetoric being used by CMP to justify their forest management practices around the corridor project, which is not following the guidelines originally put in place by the Maine DEP, which would require 50,000 acres around the project to be set aside as future mature forest, without commercial harvesting. What has now been approved is not sustainable forest management, but is rather using greenwashing rhetoric to claim they are conserving forests, they plan to harvest in the future, which will not allow trees to grow to true maturity, which is critical habitat for threatened species such as the pine marten. The corridor runs through the largest unfragmented forest east of the Mississippi river, which is a huge loss for western Maines ecology. The corridor project at least needs to be put on hold, until CMP can come up with a new development plan that makes forest conservation as a priority, as well as agreeing not to put the cost of development on rate payers.
John Tanner
Falmouth resident
3 Mustard Hollow Way Falmouth Me04205
Email ID: jtanner@maine.rr.com
Phone No.: 2077479574
10/23/2026
Please take the time needed to look at any alternate ways that this project could be done on behalf of any property owners that this will impact. It reminds me of how lucky we are having laws that ban Bill Boards on our highways. The proposed plan by CMP will be an eye sore in our neighboring communities and in Falmouth. Thank you. John Tanner
Drew Swenson
16 Woodlands Drive, Falmouth ME 04105
Email ID: dswenson@swensonandco.com
Phone No.: 2074153829
10/23/2026
Greetings: I live approx. 300 feet from the CMP right of way. Although I am supportive of the needs for A) additional electricity in the area, and B) more reliable electricity for all consumers, I am concerned by several aspects of this request for approval. I am concerned that CMP may not have adequately or correctly considered other alternatives, or the profound economic impacts to the abutters and ecosystem, by expanding the right of way and increasing pole heights. Some thoughts I have on alternatives are as follows, but I cannot determine from the submitted material whether these have been considered and the costs adequately considered. First, the St Lawrence and Atlantic railbed has sat unutilized for more than a decade. Burying cables under the former railbed removes the visual clutter of overhead towers and protects lines from high winds and ice, and is a more direct route to Portland. Although undergrounding can cost 10-15 times more than towers/lines and complicate repairs, a former rail bed does not have the same construction risks and costs of raw land. Moreover, by undergrounding in concrete casements with periodic manhole covers for repair access, the railbed allows for a much lower cost of installation and repairs, and if deep enough in the bed would allow for future rails to trails use if desired. Can the railbed be taken by eminent domain for this purpose if it is not yet publicly owned? Second, has CMP considered reconductoring. Replacing traditional wires on existing towers with advanced conductors-such as Aluminum Conductor Composite Core cables-can double or triple power capacity at a fraction of the cost and time of new lines Third, is CMPs cost analysis accurately capturing all economic costs, including property devaluation, carbon loss from tree removal, hydrological alterations, habitat loss, invasive species expansion, increased storm runoff, less photosynthesis with fewer trees, etc., etc. Thank you. Drew
WILLIAM FRANZ MULLER
UBS
4 Stormy Brook Rd., Falmouth, ME 04105
Email ID: wmuller@maine.rr.com
Phone No.: 2076712553
10/22/2026
I purchased my property in '97, fully aware that my deed granted an easement to CMP for a small power line, and a corridor of 100'. This easement covers the back 1/3 of my lot and was granted back in 1949 by the landowner at that time.I have maintained a lawn and gardens beneath the line for the enjoyment and benefit of my family. The proposed project would dramatically alter that agreement, expanding the corridor by 50%, which would extend to the edge of my back deck, and eliminate numerous trees, shrubs and landscaping, as well as dramatically changing the aesthetics of the backyard due to the size of the new poles. Additionally, I am concerned regarding the inherent safety risks of a high voltage powerline, and the utilization of herbicides in the area. Also the estimated potential reduction is my property value is in excess of $400,000. CMP sent a mailing to me as an abutter in the fall of 2025, and I went to the website, called CMP, and could get no specific information as to the nature of scope of the project. Since that time, I heard NOTHING regarding the issue until I was made aware of it in September 2026 by a group of concerned residents. CMP sent me a letter dated 9/16/26, to let me know the application was complete, and in that letter indicated that they had hosted a series of workshops for stakeholders to learn about it and provide feedback. I received NO notice of anything of that sort from CMP. I feel that CMP has been purposely opaque regarding details and impact of this project, why a project of this size is necessary, what alternatives have been considered, in order to limit negative input from residents like myself. Please DO NOT approve this project as it stands, and require CMP to be much more forthcoming regarding information about it, and how I would be impacted and compensated for any negative value. I am not inclined to grant a 50% increase in right of way easement, as it would destroy the lovely property I call home.
PXL_20261022_151120632.jpg
PXL_20261022_152048413.jpg
IMG_2402.jpeg
Wendy Barrett
2 Charlotte Drive
10/22/2026
I strongly oppose this massive power line project running so close to homes, schools and through Falmouth. The impacts to our neighborhoods, schools, children, environment, and community are significant and deserve far greater consideration. The lack of communication and transparency from CMP to Falmouth residents is deeply concerning. I only learned about this project through neighbors. Residents deserve to be informed and meaningfully involved in decisions that could permanently affect their community. Alternative routes and solutions must be thoroughly explored, including the possibility of placing the lines underground along existing railroad corridors. Creating this level of disruption in the middle of our town, without adequately exploring less damaging alternatives, is unacceptable. I live very close to Falmouth Land Trust trails where these lines would be placed and the long term impact to the community trails and neighborhoods deserve serious consideration.
Per Page
1
of
6
First
Prev
Next
Last
Go To
1
2
3
4
5
6
Notification List
Active Party List
Loading...
Name of Person/Company
Representing Company
Mailing Address
Email/Phone/Fax
Aikin, Kay E
DYNAMIC GRID
148 Middle St. Suite 1C
Portland ME 04101
Email ID: kay.aikin@INOV8futures.com
Phone Ph: 207-245-4797
Fax:
Albert, Eben M
254 Commercial St
Portland ME 04101
Email ID: ealbert@pierceatwood.com
Phone Ph: 207-791-1282
Fax:
Algeo, Benjamin
84 Marginal Way Suite 600
Portland ME 04101
Email ID: balgeo@dwmlaw.com
Phone Ph: 207-771-9218
Fax: Fax: 207-772-3627
Azzopardi, Ingrid H.
8 Charlotte Drive
FALMOUTH ME 04105
Email ID: hincki@hotmail.com
Phone Ph: 207-837-3554
Fax:
Azzopardi, Johann
8 Charlotte dr
Falmouth ME 04105 1875
Email ID: johann_azzopardi@hotmail.com
Phone Ph: 207-837-3554
Fax:
Batista, Jaime
26 Stonecrest Dr.
Falmouth ME 04105
Email ID: Jaime.h.batista@gmail.com
Phone Ph: 978-846-0889
Fax:
Becker McEntee, Rachael
ME
Email ID: rmcentee@bernsteinshur.com
Phone
Fax:
Becker, Erin Beth
10 Charlotte Drive
FALMOUTH ME 04105
Email ID: erinstaff@gmail.com
Phone Ph: 203-506-6677
Fax:
Becker, Gavin G.
10 Charlotte Drive
Falmouth ME 04105
Email ID: gavingbecker@gmail.com
Phone Ph: 781-267-2005
Fax:
Boehm, Lisa Shapiro
14 Country Lane
Falmouth ME 04105
Email ID: lboehm@maine.rr.com
Phone Ph: 207-831-9503
Fax:
Per Page
1
of
13
First
Prev
Next
Last
Go To
1
2
3
4
5
6
7
8
9
10
11
12
13
Loading...
Name of Person/Company
Representing Company
Mailing Address
Email/Phone/Fax
Aikin, Kay E
DYNAMIC GRID
148 Middle St. Suite 1C
Portland ME 04101
Email ID: kay.aikin@INOV8futures.com
Phone Ph: 207-245-4797
Fax:
Azzopardi, Ingrid H.
8 Charlotte Drive
FALMOUTH ME 04105
Email ID: hincki@hotmail.com
Phone Ph: 207-837-3554
Fax:
Azzopardi, Johann
8 Charlotte dr
Falmouth ME 04105 1875
Email ID: johann_azzopardi@hotmail.com
Phone Ph: 207-837-3554
Fax:
Batista, Jaime
26 Stonecrest Dr.
Falmouth ME 04105
Email ID: Jaime.h.batista@gmail.com
Phone Ph: 978-846-0889
Fax:
Becker McEntee, Rachael
ME
Email ID: rmcentee@bernsteinshur.com
Phone
Fax:
Becker, Erin Beth
10 Charlotte Drive
FALMOUTH ME 04105
Email ID: erinstaff@gmail.com
Phone Ph: 203-506-6677
Fax:
Becker, Gavin G.
10 Charlotte Drive
Falmouth ME 04105
Email ID: gavingbecker@gmail.com
Phone Ph: 781-267-2005
Fax:
Boehm, Lisa Shapiro
14 Country Lane
Falmouth ME 04105
Email ID: lboehm@maine.rr.com
Phone Ph: 207-831-9503
Fax:
Burnes, Ian G
151 Capital Street
Augusta ME 04330
Email ID: ian.burnes@efficiencymaine.com
Phone Ph: 207-213-4149
Fax:
Burr, Thalia
244 Middle Road
Cumberland ME 04022
Email ID: Ebhayward@hotmail.com
Phone Ph: 207-632-5063
Fax:
Per Page
1
of
9
First
Prev
Next
Last
Go To
1
2
3
4
5
6
7
8
9
Loading...
Staff Name
Role
Collins, Paulina
Hearing Examiner
Coty, Dale
Support Staff
Creamer, Robert
Hearing Examiner
Dill, Kerri
Support Staff
Dill, Kerri
Support Staff
Felt, Emily
Staff Analyst
Littlefield, Briana
Staff Analyst
McMahon, Rebecca
Lead Attorney
Mills, Amy
Reviewer
Richards, Romayn
Staff Analyst
Per Page
1
of
2
First
Prev
Next
Last
Go To
1
2